West Gate

Dhanmondi, Dhaka
Expected Completion Date December 2026
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 100%

4.Roof top design wall100 %

5.Over head water tank 100%

6.lift machine room 100%

7. Boundary wall 100%

 

06

 

 

 

Panel work & Block Work 1st floor panel work 100%, 2nd floor panel work 100%, 3rd floor panel work 100%, 4rth floor panel work 100%, 5th   panel work 100%, 6th  panel work 100%,7th floor panel work 100%,8th floor panel work 100%,9th floor panel 100%,

Block work1st floor work 100%, 2nd floor 100%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%.

07 Electrical conducting work GF 100%,1st floor 100%, 2nd Floor 100%, 3rd & 4rth floor vertical wearing 100%, 5th 100%, 6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%.
08 Door frame fitting work 2nd floor 100%,3rd floor 100%, 4rth floor 100%, 5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100%,
09 Sanitary & plumbing line work (Ac drain water line,  vertical line) GF70%,1st Floor 90%, 2nd floor 100%,3rd floor 100%,4rth floor 100%,5th floor 100%,6th floor 100%,7th floor 100%,8th floor 100%,9th floor 100% Completed
10 In side Plastering work GF ceiling plaster 100%, 1st fllor 100%,2nd floor 100%,3rd floor 100%,4rth floor100%,5th floor100%,6th floor100%, 7th floor 100%, 8th floor 100%, 9th floor 100%.

G.f Wall plaster 70%,1st floor wall plaster 97%,2nd floor 96%, 3rd floor 100%,4rth floor 100%,5th floor 100%,6th 100%,7th 100%,8th 100%,9th floor 100%.

 

 

 

10 Electrical cable wiring work A9 95%, B9 95%,A8 95%, B8 95%, A7 95%, B7 95%,A6 95%, B6 95%, A5 95%, B5 95%, A4 90%, B4 90%,A3 80%, B3 80%,A2 70%, B2 70%,1st 60%
11 Wall tiles work A2 100%, B2 100%,A3 100%, B3 100%, A4 100%, B4 100%, A5 100%, B5 100%, A6 100%,B6 100%, A7 100%, B7 100%, A8 100%, B8 100%,  A9 100%, B9 100%, & OHWT 100%, UGWT 100%,
12 Common sanitary & Plumbing line work 80%
13 Outside plastering work 100%
14 Floor tiles A2 100%, B2 100%, A3 100%,B3 100%,A4 100%, B4 100%, A5 100%,A6 100%, B5 100%, A7 100%, B7 100%, A8 100%, B8 100%, A9 100%, B9 100%. Mazanine 100%, OHWT 100%, & Stair 98% , Roof Top 90%,
14 L.C.C work 100%
15 Grill & Railing work 98%
16 Inside paint & Polishing work 1st Coat A280%, A3 100%,B3 100%, A4 100%,B4 100%,A6 100%,B6 100%,A7 100%,B7 100%, A8 100%, B8 100%, A9 100%, B9 100%.

 

2nd Coat A2 50%, A3 100%,B3 100%, A4 100%,B4 100%,A6 100%,B6 100%,A7 100%,B7 100%, A8 100%, B8 100%, A9 100%, B9 100%.

 

 

 

17 Switch -Socket fitting work A4 90%,B4 90%,A5 90%,B5 90%,A6 80%,B6 80%,A7 80%,B7 80%,

A8 100%,B8 100%, A9 80%,B9 90%

18 Outside paint work 1st Coat 60%
19 Door shutter work A2 50%,B2 50%,A3 50%, B3 50%,A4 50%,B4 50%,A5 50%,B5 50%, A6 50%,B6 50%, A7 50%,B7 50%, A8 100%, B8 100%, A9 50%,B9 50%
20 Aluminum/Glazing work A3 50%, B3 50%,A4 50%,B4 50%,A5 50%,B5 50%, A6 50%, A7 50%,B7 50%, A8 100%, B8 100%, A9 50%,B9 50%
21 Tiles Pointing work & Marble finishing work A3 50%, B3 50%,A4 50%,B4 50%,A5 50%,B5 50%, A6 50%, A7 50%,B7 50%, A8 100%, B8 100%, A9 50%,B9 50%,,
22 Commode – Basin fitting work and C.P fittings work  A9 100%,B9 100%, A8 100%,B8 100%,A7100%,B7100%,B6 100%,
23 Lift/Generator /Substation /Solar work 40% Completed
24 Boundary wall /Ground floor development work 95 %. Completed
25 Roof top finishing work  90% Completed
26 Roof top Gardening work 70% Completed

 