Welcome Home

Mirpur, Dhaka
Expected Completion Date December 2026
Status Updated September, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

Name of the work Progress details
Foundation work 100% Completed
Super Structure work 98% completed
Block work. A Type =100%

B Type =98%

C Type =100%

D Type =100%

E Type =100%

F Type =100%

G Type =100%

H Type =100%

I Type =100%

J Type =95%

K Type =100%

Conduit Pipe Work A Type =100%

B Type =100%

C Type =100%

D Type =100%

E Type =100%

F Type =100%

G Type =100%

H Type =100%

I Type =100%

J Type =100%

K Type =100%

Door frame fitting work A Type =100%

B Type =100%

C Type =100%

D Type =100%

E Type =100%

F Type =100%

G Type =100%

H Type =100%

I Type =100%

J Type =95%

K Type =100%

Sanitary & plumbing line work A Type =100%

B Type =100%

C Type =100%

D Type =100%

E Type =100%

F Type =100%

G Type =100%

H Type =80%

I Type =80%

J Type =55%

K Type =90%

In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 98%,

1st Floor Ceiling= 95%,

2nd Floor Ceiling= 100%

3rd Floor Ceiling=100%,

4th Floor Ceiling=100%,

5th Floor Ceiling=100%,

6th Floor Ceiling=100%,

7th Floor Ceiling=100%,

8th Floor Ceiling=100%,

9th Floor Ceiling=100%,

10th Floor Ceiling=100%,

11th Floor Ceiling=100%,

12th Floor Ceiling=100%,

13th Floor Ceiling=100%,

Inside Wall Plaster:

1st floor 90%,

2nd floor 100%

3rd floor 100%

4th floor 100%

5th floor 100%

6th floor 100%

7th floor 100%

8th floor 100%

9th floor 100%

10th floor 100%

11th floor 100%

12th floor 100%

13th floor 100%

Electrical cable wiring work Basement= 95%,

Ground Floor=60%

1st floor 15%,

2nd floor 80%

3rd floor 100%

4th floor 100%

5th floor 85%

6th floor 85%

7th floor 85%

8th floor 60%

9th floor 70%

10th floor 60%

11th floor 60%

12th floor 60%

13th floor 60%

Wall tiles work Wall tiles work

1st floor 40%,

2nd floor 95%

3rd floor 95%

4th floor 95%

5th floor 95%

6th floor 95%

7th floor 95%

8th floor 95%

9th floor 95%

10th floor 95%

11th floor 95%

12th floor 95%

13th floor 95%

Common sanitary & Plumbing line work GF Floor = 00%,

1st Floor = 40%,

2nd Floor = 85%

3rd Floor = 85%,

4th Floor = 85%,

5th Floor = 85%,

6th Floor = 85%,

7th floor 85%

8th floor 85%

9th floor 85%

10th floor 85%

11th floor 85%

12th floor 85%

13th floor 85%

Outside plastering work Outside Wall Plaster:

13th floor 100%

12th floor 100%

11th floor 100%

10th floor 100%

09th floor 100%

08th floor 100%

07th floor 100%

06th floor 100%

05th floor 100%

04th floor 100%

03th floor 100%

02th floor 100%

01th floor 30%

Floor tiles/Marble work/Granait work Floor tiles work:

1st floor 70%,

2nd floor 90%

3rd floor 95%

4th floor 95%

5th floor 80%

6th floor 90%

7th floor 95%

8th floor 95%

9th floor 95%

10th floor 95%

11th floor 95%

12th floor 95%

13th floor 95%

 

Granait work:

1st floor 25%,

2nd floor 100%

3rd floor 100%

4th floor 100%

6th floor 100%

7th floor 100%

8th floor 100%

9th floor 100%

10th floor 100%

11th floor 100%

12th floor 100%

13th floor 100%

 

Marble work:

1st floor 35%,

2nd floor 90%

3rd floor 90%

4th floor 90%

6th floor 90%

7th floor 90%

8th floor 90%

9th floor 90%

10th floor 90%

11th floor 90%

12th floor 90%

13th floor 90%

L.C.C work 95% Done
Grill & Railing work 1st floor 25%,

2nd floor 60%

3rd floor 85%

4th floor 85%

5th floor 85%

6th floor 85%

7th floor 85%

8th floor 85%

9th floor 85%

10th floor 85%

11th floor 85%

12th floor 85%

13th floor 85%

Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work. 13th floor 05%

12th floor 05%

11th floor 05%

10th floor 05%

09th floor 05%

08th floor 05%

Aluminum/Glazing work Aluminum:

13th floor 10%

12th floor 10%

11th floor 10%

 

Tiles Pointing work & Marble finishing work 13th floor 05%

12th floor 05%

11th floor 05%

10th floor 05%

09th floor 05%

08th floor 05%

07th floor 05%

06th floor 05%

05th floor 05%

04th floor 05%

03th floor 05%

 

Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work Boundary wall = 80%
Roof top finishing work Work Done= 20%
Roof top Gardening work Work Done= 05%