Construction progress details
The progress table comes directly from the WordPress post content.
| Name of the work | Progress details |
| Foundation work | 100% Completed |
| Super Structure work | 98% completed |
| Block work. | A Type =100%
B Type =98% C Type =100% D Type =100% E Type =100% F Type =100% G Type =100% H Type =100% I Type =100% J Type =95% K Type =100% |
| Conduit Pipe Work | A Type =100%
B Type =100% C Type =100% D Type =100% E Type =100% F Type =100% G Type =100% H Type =100% I Type =100% J Type =100% K Type =100% |
| Door frame fitting work | A Type =100%
B Type =100% C Type =100% D Type =100% E Type =100% F Type =100% G Type =100% H Type =100% I Type =100% J Type =95% K Type =100% |
| Sanitary & plumbing line work | A Type =100%
B Type =100% C Type =100% D Type =100% E Type =100% F Type =100% G Type =100% H Type =80% I Type =80% J Type =55% K Type =90% |
| In side Plastering work | Tower1&2, Basement Ceiling=95%
GF Ceiling= 98%, 1st Floor Ceiling= 95%, 2nd Floor Ceiling= 100% 3rd Floor Ceiling=100%, 4th Floor Ceiling=100%, 5th Floor Ceiling=100%, 6th Floor Ceiling=100%, 7th Floor Ceiling=100%, 8th Floor Ceiling=100%, 9th Floor Ceiling=100%, 10th Floor Ceiling=100%, 11th Floor Ceiling=100%, 12th Floor Ceiling=100%, 13th Floor Ceiling=100%, Inside Wall Plaster: 1st floor 90%, 2nd floor 100% 3rd floor 100% 4th floor 100% 5th floor 100% 6th floor 100% 7th floor 100% 8th floor 100% 9th floor 100% 10th floor 100% 11th floor 100% 12th floor 100% 13th floor 100% |
| Electrical cable wiring work | Basement= 95%,
Ground Floor=60% 1st floor 15%, 2nd floor 80% 3rd floor 100% 4th floor 100% 5th floor 85% 6th floor 85% 7th floor 85% 8th floor 60% 9th floor 70% 10th floor 60% 11th floor 60% 12th floor 60% 13th floor 60% |
| Wall tiles work | Wall tiles work
1st floor 40%, 2nd floor 95% 3rd floor 95% 4th floor 95% 5th floor 95% 6th floor 95% 7th floor 95% 8th floor 95% 9th floor 95% 10th floor 95% 11th floor 95% 12th floor 95% 13th floor 95% |
| Common sanitary & Plumbing line work | GF Floor = 00%,
1st Floor = 40%, 2nd Floor = 85% 3rd Floor = 85%, 4th Floor = 85%, 5th Floor = 85%, 6th Floor = 85%, 7th floor 85% 8th floor 85% 9th floor 85% 10th floor 85% 11th floor 85% 12th floor 85% 13th floor 85% |
| Outside plastering work | Outside Wall Plaster:
13th floor 100% 12th floor 100% 11th floor 100% 10th floor 100% 09th floor 100% 08th floor 100% 07th floor 100% 06th floor 100% 05th floor 100% 04th floor 100% 03th floor 100% 02th floor 100% 01th floor 30% |
| Floor tiles/Marble work/Granait work | Floor tiles work:
1st floor 70%, 2nd floor 90% 3rd floor 95% 4th floor 95% 5th floor 80% 6th floor 90% 7th floor 95% 8th floor 95% 9th floor 95% 10th floor 95% 11th floor 95% 12th floor 95% 13th floor 95%
Granait work: 1st floor 25%, 2nd floor 100% 3rd floor 100% 4th floor 100% 6th floor 100% 7th floor 100% 8th floor 100% 9th floor 100% 10th floor 100% 11th floor 100% 12th floor 100% 13th floor 100%
Marble work: 1st floor 35%, 2nd floor 90% 3rd floor 90% 4th floor 90% 6th floor 90% 7th floor 90% 8th floor 90% 9th floor 90% 10th floor 90% 11th floor 90% 12th floor 90% 13th floor 90% |
| L.C.C work | 95% Done |
| Grill & Railing work | 1st floor 25%,
2nd floor 60% 3rd floor 85% 4th floor 85% 5th floor 85% 6th floor 85% 7th floor 85% 8th floor 85% 9th floor 85% 10th floor 85% 11th floor 85% 12th floor 85% 13th floor 85% |
| Inside paint & Polishing work | N/A |
| Switch -Socket fitting work | N/A |
| Outside paint work | N/A |
| Door shutter work. | 13th floor 05%
12th floor 05% 11th floor 05% 10th floor 05% 09th floor 05% 08th floor 05% |
| Aluminum/Glazing work | Aluminum:
13th floor 10% 12th floor 10% 11th floor 10%
|
| Tiles Pointing work & Marble finishing work | 13th floor 05%
12th floor 05% 11th floor 05% 10th floor 05% 09th floor 05% 08th floor 05% 07th floor 05% 06th floor 05% 05th floor 05% 04th floor 05% 03th floor 05%
|
| Commode – Basin fitting work and C.P fittings work | N/A |
| Lift/Generator /Substation /Solar work | N/A |
| Boundary wall /Ground floor development work | Boundary wall = 80% |
| Roof top finishing work | Work Done= 20% |
| Roof top Gardening work | Work Done= 05% |