Valencia

Uttara, Dhaka
Expected Completion Date December 2026
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
1 Foundation work 100% Completed
2 Super Structure work Tower-1: Ground floor slab 100%,1st floor slab 100%,2nd floor slab 100%,3rd floor slab 100%,4th floor slab 100%.

5th floor 100%, 5th floor column 100%.

6th floor slab 100%, 7th floor slab 100%.

8th floor column 100%,8th floor slab 100%.

 

Tower-2: 1st floor slab 100%,2nd floor slab 100%, 3rd floor slab 100% ,4th floor slab 100%. 5th floor slab 100%. 6th floor slab 100%, 6th floor column 100%,7th floor slab 100%, 8th floor column 100% 8th floor slab 100% 9th floor column 100%,9th Floor Slab 100%

 

3 Block work Tower-1: Ground floor Substation room, Stair wall 98%. 1st floor 98%, 2nd floor 100%, 3rd floor 100%, 4th floor 100%,5th floor 100%, 6th floor 100%,7th floor 100% 8TH Floor100 %

 

Tower-2: 1st floor 100%, 2nd floor 100%,3rd floor 100%, 4th floor 100%, 5th floor 100%,6th Floor 100% 7th Floor 100% 8th Floor 100% 9th Floor 90%

4 Electrical  conduit work Tower-1: 1st floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%,4th floor slab conduiting 100%,5th floor slab conduiting 100%. 6th floor slab 100%,7th floor 100%, 8th floor slab 100%, 9th floor slab 100%

 

Tower-2:1st floor floor slab conduiting100%, 2nd  floor slab conduiting 100%, 3rd floor slab conduiting 100%. 4th floor slab 100%,5th floor 100%,6th floor slab 100%,7th floor slab 100%. 8th floor slab 100% 9th floor slab100%

5 Door frame fitting work 98 % Completed
6 Sanitary & plumbing line  work 86% Completed
7 In side Ceiling Plaster & Wall Plaster work Tower-1 Basement ceiling Plaster 100%,

Ground floor ceiling Plaster 100%, 2nd floor celling 100%, 4th floor 100%,5th floor 100%, 6th floor slab 100%,7th floor 100%, 8th floor ceiling plaster 100%. Basement wall Plaster 95%,2nd floor wall Plaster 100%,3rd Floor wall plaster100% 4th Floor wall plaster 100%,5th Floor wall Plaster 100%, 6th floor wall plaster 100%, 7th floor wall plaster 100%,8th floor wall plaster 100%

 

Tower-2 1st floor celling 100%,2nd floor ceiling 100%, 3rd floor 100%, 4th floor 100%, 5th floor 100%,6th floor 100% 7th Floor plaster 100% ,8th floor ceiling plaster 100%,9th Floor ceiling plaster 100%….1st floor wall Plaster 100%,2nd floor Wall plaster 100%,3rd floor wall plaster 100%,4th floor wall plaster 100%, 5th Floor wall plaster 100%,6th floor wall plaster 90%,7th floor wall plaster 100% 8th floor wall plaster 100% 9th floor wall plaster 100%

8 Electrical cable wiring work Basement 80%, Ground floor 90%.
9 Wall tiles  work 95% Completed
10 Common sanitary & Plumbing line work 80% Completed
11 Outside plastering work 100% Completed
12 Floor tiles/Marble work 90% Completed
13 L.C.C work 100% Completed
14 Grill & Railing work 90% Completed
15 Inside paint & Polishing work 50% Completed
16 Switch -Socket fitting work Not Yet Started
17 Outside paint work 30% Completed
18 Door shutter work 20 % Completed
19 Aluminum/Glazing work 40% Completed
20 Tiles Pointing work & Marble finishing work 35% Completed
21 Commode – Basin fitting work and C.P fittings work 30% Completed
22 Lift/Generator /Substation /Solar work 50% Completed
23 Boundary wall /Ground floor development work 70% Completed
24 Roof top finishing work 95% Completed
25 Roof top Gardening work 40% Completed