Construction progress details
The progress table comes directly from the WordPress post content.
| SL. No | Name of the work | Progress details |
| 1 | Foundation work | 100% Completed |
| 2 | Super Structure work | Tower-1: Ground floor slab 100%,1st floor slab 100%,2nd floor slab 100%,3rd floor slab 100%,4th floor slab 100%.
5th floor 100%, 5th floor column 100%. 6th floor slab 100%, 7th floor slab 100%. 8th floor column 100%,8th floor slab 100%.
Tower-2: 1st floor slab 100%,2nd floor slab 100%, 3rd floor slab 100% ,4th floor slab 100%. 5th floor slab 100%. 6th floor slab 100%, 6th floor column 100%,7th floor slab 100%, 8th floor column 100% 8th floor slab 100% 9th floor column 100%,9th Floor Slab 100%
|
| 3 | Block work | Tower-1: Ground floor Substation room, Stair wall 98%. 1st floor 98%, 2nd floor 100%, 3rd floor 100%, 4th floor 100%,5th floor 100%, 6th floor 100%,7th floor 100% 8TH Floor100 %
Tower-2: 1st floor 100%, 2nd floor 100%,3rd floor 100%, 4th floor 100%, 5th floor 100%,6th Floor 100% 7th Floor 100% 8th Floor 100% 9th Floor 90% |
| 4 | Electrical conduit work | Tower-1: 1st floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%,4th floor slab conduiting 100%,5th floor slab conduiting 100%. 6th floor slab 100%,7th floor 100%, 8th floor slab 100%, 9th floor slab 100%
Tower-2:1st floor floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%. 4th floor slab 100%,5th floor 100%,6th floor slab 100%,7th floor slab 100%. 8th floor slab 100% 9th floor slab100% |
| 5 | Door frame fitting work | 98 % Completed |
| 6 | Sanitary & plumbing line work | 86% Completed |
| 7 | In side Ceiling Plaster & Wall Plaster work | Tower-1 Basement ceiling Plaster 100%,
Ground floor ceiling Plaster 100%, 2nd floor celling 100%, 4th floor 100%,5th floor 100%, 6th floor slab 100%,7th floor 100%, 8th floor ceiling plaster 100%. Basement wall Plaster 95%,2nd floor wall Plaster 100%,3rd Floor wall plaster100% 4th Floor wall plaster 100%,5th Floor wall Plaster 100%, 6th floor wall plaster 100%, 7th floor wall plaster 100%,8th floor wall plaster 100%
Tower-2 1st floor celling 100%,2nd floor ceiling 100%, 3rd floor 100%, 4th floor 100%, 5th floor 100%,6th floor 100% 7th Floor plaster 100% ,8th floor ceiling plaster 100%,9th Floor ceiling plaster 100%….1st floor wall Plaster 100%,2nd floor Wall plaster 100%,3rd floor wall plaster 100%,4th floor wall plaster 100%, 5th Floor wall plaster 100%,6th floor wall plaster 90%,7th floor wall plaster 100% 8th floor wall plaster 100% 9th floor wall plaster 100% |
| 8 | Electrical cable wiring work | Basement 80%, Ground floor 90%. |
| 9 | Wall tiles work | 95% Completed |
| 10 | Common sanitary & Plumbing line work | 80% Completed |
| 11 | Outside plastering work | 100% Completed |
| 12 | Floor tiles/Marble work | 90% Completed |
| 13 | L.C.C work | 100% Completed |
| 14 | Grill & Railing work | 90% Completed |
| 15 | Inside paint & Polishing work | 50% Completed |
| 16 | Switch -Socket fitting work | Not Yet Started |
| 17 | Outside paint work | 30% Completed |
| 18 | Door shutter work | 20 % Completed |
| 19 | Aluminum/Glazing work | 40% Completed |
| 20 | Tiles Pointing work & Marble finishing work | 35% Completed |
| 21 | Commode – Basin fitting work and C.P fittings work | 30% Completed |
| 22 | Lift/Generator /Substation /Solar work | 50% Completed |
| 23 | Boundary wall /Ground floor development work | 70% Completed |
| 24 | Roof top finishing work | 95% Completed |
| 25 | Roof top Gardening work | 40% Completed |