The Peak

ECB Circle, Dhaka
Expected Completion Date October 2027
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 99% Completed
  Block work 80%
  Electrical conduit work 70% Completed
  Door frame fitting work 40%
  Sanitary & plumbing line work 22%
  In side Plastering work 48% Complete
  Electrical cable wiring work 05% Complete
  Wall tiles work N/A
  Common sanitary & Plumbing line work N/A
  Outside plastering work 05%
  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work N/A
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work N/A
  Roof top finishing work N/A
  Roof top Gardening work N/A