The Madison

Uttara, Dhaka
Expected Completion Date December 2026
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
1 Foundation work 100% Completed.
2 Basement work 100% Completed.
3 Super Structure work 100% completed. (T-1- 11th F roof Completed, T-2 – 11th F roof Completed. T-3 – 10F roof Completed, T-4 – 10F Roof Completed)
4 Block Work 100% completed.
5 Electrical conduiting work 99% Completed.
6 Door frame fitting work 100% Completed.
7 Sanitary & plumbing line work 99% Completed.
8 Inside Plastering work 99% Completed.
9 Electrical cable wiring work 99% Completed.
10 Wall tiles work 98%completed
11 Common sanitary & Plumbing line work 90% completed
12 Outside plastering work 100%Completed.
13 Floor tiles/Marble work 98% completed.
14 L.C.C work 100% Completed.
15 Grill & Railing work 97% completed.
16 Inside paint & Polishing work 85% completed.
17 Switch -Socket fitting work 88% completed.
18 Outside paint work 55% completed.
19 Door shutter work 98%completed.
20 Aluminum work 95% completed.
21 Tiles Pointing work & Marble finishing work 88% completed.
22 Commode – Basin fitting work and C.P fittings work 87% completed.
23 Lift/Generator /Substation /Solar work 90% completed.
24 Boundary wall /Ground floor development work 90% Completed.
25 Roof top finishing work 80% Completed.
26 Roof top Gardening work G.F Garden work 75% completed.
27 Land escape /Logo work 60%