Construction progress details
The progress table comes directly from the WordPress post content.
| SL. No | Name of the work | Progress details |
| 1 | Foundation work | 100% Completed. |
| 2 | Basement work | 100% Completed. |
| 3 | Super Structure work | 100% completed. (T-1- 11th F roof Completed, T-2 – 11th F roof Completed. T-3 – 10F roof Completed, T-4 – 10F Roof Completed) |
| 4 | Block Work | 100% completed. |
| 5 | Electrical conduiting work | 99% Completed. |
| 6 | Door frame fitting work | 100% Completed. |
| 7 | Sanitary & plumbing line work | 99% Completed. |
| 8 | Inside Plastering work | 99% Completed. |
| 9 | Electrical cable wiring work | 99% Completed. |
| 10 | Wall tiles work | 98%completed |
| 11 | Common sanitary & Plumbing line work | 90% completed |
| 12 | Outside plastering work | 100%Completed. |
| 13 | Floor tiles/Marble work | 98% completed. |
| 14 | L.C.C work | 100% Completed. |
| 15 | Grill & Railing work | 97% completed. |
| 16 | Inside paint & Polishing work | 85% completed. |
| 17 | Switch -Socket fitting work | 88% completed. |
| 18 | Outside paint work | 55% completed. |
| 19 | Door shutter work | 98%completed. |
| 20 | Aluminum work | 95% completed. |
| 21 | Tiles Pointing work & Marble finishing work | 88% completed. |
| 22 | Commode – Basin fitting work and C.P fittings work | 87% completed. |
| 23 | Lift/Generator /Substation /Solar work | 90% completed. |
| 24 | Boundary wall /Ground floor development work | 90% Completed. |
| 25 | Roof top finishing work | 80% Completed. |
| 26 | Roof top Gardening work G.F Garden work | 75% completed. |
| 27 | Land escape /Logo work | 60% |