The Lighthouse

Bashundhara R/A, Dhaka
Expected Completion Date February 2028
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work 100% Completed
02 Super Structure work 85% Completed
03 Block work 87% Completed
04 Electrical  conduit  work 45% Completed
05 Door frame fitting work 48% Completed
06 Sanitary & plumbing line  work 7% Completed
07 In side Plastering work 45% Completed
08 Electrical cable wiring work N/A
09 Wall tiles  work N/A
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 25%
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 42% Completed
24 Roof top finishing work 45%
25 Roof top Gardening work 5%

 