Sunny Hill

Mirpur, Dhaka
Expected Completion Date July 2027
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
1 Foundation work 100% Completed
2 Super Structure work 100%
3 Block work 98%
4 Electrical conduit work 90%
5 Door frame fitting work 95%
6 Sanitary & plumbing line work 85%
7 In side Plastering work 95%
8 Electrical cable wiring work 70%
9 Wall tiles work 60%
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 90%
12 Floor tiles/Marble work 60%
13 L.C.C work N/A
14 Grill & Railing work 50%
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 70%
24 Roof top finishing work 35%
25 Roof top Gardening work 30%

 