Silvi

Gulshan, Dhaka
Expected Completion Date December 2026
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Footing casting 100% completed, Mat casting 100% completed, retaining wall 100% completed, Basement roof 100% completed.
02 Super Structure work 100% Completed. (G.F 100%, 1st Floor Roof Slab -100%, 2nd Floor Roof Slab -100%, 3rd Floor Roof Slab -100%, 4th Floor Roof Slab -100% completed. 5th floor roof slab 100% completed), 6th floor roof slab 100% completed, 7th floor roof slab 100% completed, 8th floor slab 100% completed.
03 Partition Wall Work 100% Completed.
04 Electrical conducting work 97% Completed.
05 Door frame fitting work 100% completed.
06 Sanitary & plumbing line work 96% completed.
07 In side Plastering work 100% completed.
08 Electrical cable wiring work 98% completed.
09 Wall tiles work 99% completed.
10 Common sanitary & Plumbing line work 95% Completed.
11 Outside plastering work 99% Completed.
12 Floor tiles/Marble work 99% completed.
13 L.C.C work Not Yet Started.
14 Grill & Railing work 100% completed.
15 Inside paint & Polishing work 50% completed
16 Switch -Socket fitting work 50% completed
17 Outside paint work 5% completed
18 Door shutter work 60% completed
19 Aluminum/Glazing work 80% completed
20 Tiles Pointing work & Marble finishing work 15% completed
21 Commode – Basin fitting work and C.P fittings work 40% completed
22 Lift/Generator /Substation /Solar work 80% completed
23 Boundary wall /Ground floor development work 2% completed
24 Roof top finishing work Not Yet Started.
25 Roof top Gardening work Construction work 90%