Resonance

Adabor, Dhaka
Expected Completion Date December 2026
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 100 % completed.
03 Block Work A-1 =100%, A-2= 100%, A-3= 100%, A-4 =100%, A-5= 100%, A-6= 100%, A-7= 100%,A-8=100%,A-9=100%  B-1=100%, B-2=100%,B-3 = 100%, B-4=100%, B-5=100%,  B-6=100%,  B-7=100%, B-8=100%,B-9=100%  C-1=100%, C-2=100%, C-3 =100%, C-4 =100%, C-5 =100%, C-6 =100 %, C-7 =100%, C-8= 100%,C-9=100%I-2 (D2)=100% , D-3= 100%, D-4= 100%, D-5= 100%, D-6= 100%,D-7=100%,D-8=100%,D-9=100% E-2 = 100%, E-3=100%

E-4= 100%, E100% F-2 =100%, F-3 =100%, F-4=100%, F-5=100%, F-6=100%, F-7=100%, F-8=100%,F-9=100% G-2=100%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=100%, G-8=95%,G-9=100%

04 Electrical conducting work A-1 =100%, A-2= 100%, A-3= 100%, A-4 =100%, A-5= 100%, A-6= 100%, A-7= 100%,A-8=100%,A-9=100%  B-1=100%, B-2=100%,B-3 = 100%, B-4=100%, B-5=100%,  B-6=100%,  B-7=100%, B-8=100%,B-9=100%  C-1=100%, C-2=100%, C-3 =100%, C-4 =100%, C-5 =100%, C-6 =100 %, C-7 =100%, C-8= 100%,C-9=100%I-2 (D2)=100% , D-3= 100%, D-4= 100%, D-5= 100%, D-6= 100%,D-7=100%,D-8=100%,D-9=100% E-2 = 100%, E-3=100%

E-4= 100%, E100% F-2 =100%, F-3 =100%, F-4=100%, F-5=100%, F-6=100%, F-7=100%, F-8=100%,F-9=100% G-2=100%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=100%, G-8=95%,G-9=100%

05 Door frame fitting work 100% completed
06 Sanitary & plumbing line work 80% completed
07 In side Plastering work A-1 =100%, A-2= 100%, A-3= 100%, A-4 =100%, A-5= 100%, A-6= 100%, A-7= 100%,A-8=100%,A-9=100%  B-1=100%, B-2=100%,B-3 = 100%, B-4=100%, B-5=100%,  B-6=100%,  B-7=100%, B-8=100%,B-9=60%  C-1=100%, C-2=100%, C-3 =100%, C-4 =100%, C-5 =100%, C-6 =100 %, C-7 =100%, C-8= 100%,C-9=70%I-2 (D2)=100% , D-3= 100%, D-4= 100%, D-5= 100%, D-6= 100%,D-7=100%,D-8=100%,D-9=40% E-2 = 100%, E-3=100%

E-4= 100%, E100% F-2 =100%, F-3 =100%, F-4=100%, F-5=100%, F-6=100%, F-7=100%, F-8=100%,F-9=60% G-2=100%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=100%, G-8=95%,G-9=90%

08 Electrical cable wiring work 95% completed
09 Wall tiles work 90% completed
10 Common sanitary & Plumbing line work 70% completed
11 Outside plastering work 95% completed
12 Floor tiles/Marble work 90% completed
13 L.C.C work 100% completed
14 Grill & Railing work 80% completed
15 Inside paint & Polishing work 40% completed
16 Switch -Socket fitting work 50% completed
17 Outside paint work 30% completed
18 Door shutter work 60% completed
19 Aluminum work 50% completed
20 Tiles Pointing work & Marble finishing work 30% completed
21 Commode – Basin fitting work and C.P fittings work 20% completed
22 Lift/Generator /Substation /Solar work 80% completed
23 Boundary wall /Ground floor development work 60% completed.
24 Roof top finishing work 80% completed.
25 Roof top Gardening work G.F Garden work 60% completed.