Construction progress details
The progress table comes directly from the WordPress post content.
| SL | Name of the work | Progress details |
| 01 | Foundation work | 100% completed |
| 02 | Basement work | N/A |
| 03 | Super Structure work | 100% completed |
| 04 | Block Work | 100% completed |
| 05 | Electrical conduiting work | 96% completed |
| 06 | Door frame fitting work | 80% completed |
| 07 | Sanitary & plumbing line work | 75% completed |
| 08 | Inside Plastering work | 92% completed |
| 09 | Electrical cable wiring work | 35% completed |
| 10 | Wall tiles work | 20% Completed |
| 11 | Common sanitary & Plumbing line work | 60% Completed |
| 12 | Outside plastering work | 92% completed |
| 13 | Floor tiles/Marble work | 20% Completed |
| 14 | L.C.C work | 100 % completed |
| 15 | Grill & Railing work | 85% Completed |
| 16 | Inside paint & Polishing work | Not Yet Started |
| 17 | Switch -Socket fitting work | Not Yet Started |
| 18 | Outside paint work | Not Yet Started |
| 19 | Door shutter work | Not Yet Started |
| 20 | Aluminum work | Not Yet Started |
| 21 | Tiles Pointing work & Marble finishing work | Not Yet Started |
| 22 | Commode – Basin fitting work and C.P fittings work | Not Yet Started |
| 23 | Lift/Generator /Substation /Solar work | Not Yet Started |
| 24 | Boundary wall /Ground floor development work | 70% completed |
| 25 | Roof top finishing work | 40% completed. |
| 26 | Roof top Gardening work G.F Garden work | Not Yet Started |
| 27 | Land escape /Logo work | Not Yet Started |