Pleasant Homes

Uttara, Dhaka
Expected Completion Date October 2027
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL Name of the work Progress details
01 Foundation work 100% completed
02 Basement work N/A
03 Super Structure work 100% completed
04 Block Work 100% completed
05 Electrical conduiting work 96% completed
06 Door frame fitting work 80% completed
07 Sanitary & plumbing line work 75% completed
08 Inside Plastering work 92% completed
09 Electrical cable wiring work 35% completed
10 Wall tiles work 20% Completed
11 Common sanitary & Plumbing line work 60% Completed
12 Outside plastering work 92% completed
13 Floor tiles/Marble work 20% Completed
14 L.C.C work 100 % completed
15 Grill & Railing work 85% Completed
16 Inside paint & Polishing work Not Yet Started
17 Switch -Socket fitting work Not Yet Started
18 Outside paint work Not Yet Started
19 Door shutter work Not Yet Started
20 Aluminum work Not Yet Started
21 Tiles Pointing work & Marble finishing work Not Yet Started
22 Commode – Basin fitting work and C.P fittings work Not Yet Started
23 Lift/Generator /Substation /Solar work Not Yet Started
24 Boundary wall /Ground floor development work 70% completed
25 Roof top finishing work 40% completed.
26 Roof top Gardening work G.F Garden work Not Yet Started
27 Land escape /Logo work Not Yet Started

 