Construction progress details
The progress table comes directly from the WordPress post content.
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | Footing 100% completed, |
| 02 | Super Structure work | Up to 13th floor roof slab 100% done. OHWT RCC work 100%, Parapet wall 100 % done. Swimming pool RCC Work 100% done |
| 03 | Block Work | 93% completed |
| 04 | Electrical conduiting work | 90% completed
|
| 05 | Door frame fitting work | 93% completed
|
| 06 | Sanitary & plumbing line work. | Vertical duct (10 no’s) line 88% done |
| 07 | In side Plastering work | Ceiling plaster 95% completed |
| Wall plaster- 85% completed | ||
| 08 | Electrical cable wiring work | 10% Completed |
| 09 | Wall tiles work | 20% Completed |
| 10 | Common sanitary & Plumbing line work | 60% Completed |
| 11 | Outside plastering work | 40% Completed |
| 12 | Floor tiles/Marble work | 22% Completed |
| 13 | L.C.C work | Not Yet Started. |
| 14 | Grill & Railing work | 10% Completed |
| 15 | Inside paint & Polishing work | Not Yet Started. |
| 16 | Switch -Socket fitting work | Not Yet Started. |
| 17 | Outside paint work | Not Yet Started. |
| 18 | Door shutter work | Not Yet Started. |
| 19 | Aluminum/Glazing work | Not Yet Started. |
| 20 | Tiles Pointing work & Marble finishing work | Not Yet Started. |
| 21 | Commode – Basin fitting work and C.P fittings work | Not Yet Started. |
| 22 | Lift/Generator /Substation /Solar work | Not Yet Started. |
| 23 | Boundary wall /Ground floor development work | Not Yet Started. |
| 24 | Roof top finishing work | Not Yet Started. |
| 25 | Roof top Gardening work | Not Yet Started. |