Magnifico

Gulshan, Dhaka
Expected Completion Date November 2027
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Footing 100% completed,
02 Super Structure work Up to 13th floor roof slab 100% done. OHWT RCC work 100%, Parapet wall 100 % done. Swimming pool RCC Work 100% done
03 Block Work 93% completed
04 Electrical conduiting work 90% completed

 

05 Door frame fitting work 93% completed

 

06 Sanitary & plumbing line work. Vertical duct (10 no’s) line 88% done
07 In side Plastering work Ceiling plaster 95% completed
Wall plaster- 85% completed
08 Electrical cable wiring work 10% Completed
09 Wall tiles work 20% Completed
10 Common sanitary & Plumbing line work 60% Completed
11 Outside plastering work 40% Completed
12 Floor tiles/Marble work 22% Completed
13 L.C.C work Not Yet Started.
14 Grill & Railing work 10% Completed
15 Inside paint & Polishing work Not Yet Started.
16 Switch -Socket fitting work Not Yet Started.
17 Outside paint work Not Yet Started.
18 Door shutter work Not Yet Started.
19 Aluminum/Glazing work Not Yet Started.
20 Tiles Pointing work & Marble finishing work Not Yet Started.
21 Commode – Basin fitting work and C.P fittings work Not Yet Started.
22 Lift/Generator /Substation /Solar work Not Yet Started.
23 Boundary wall /Ground floor development work Not Yet Started.
24 Roof top finishing work Not Yet Started.
25 Roof top Gardening work Not Yet Started.