Construction progress details
The progress table comes directly from the WordPress post content.
| SL. No | Name of the work | Location | Progress details | Remarks |
| 01 | Foundation work | 100% completed | ||
| 02 | Super Structure work | 7th floor | Roof slab casting complete | |
| 03 | Block Work | Apartment =A1
Apartment=A2 Apartment=A3 Apartment=A4 Apartment=A5 Apartment=A6
|
80% Complete
80% Complete 100% Complete 100% Complete 60% Complete 50% Complete
|
|
| 04 | Electrical conduiting work | Apartment =A1
Apartment=A2 Apartment=A3 Apartment=A4 Apartment=A5 Apartment=A5
|
20% Complete
340% Complete 40% Complete 40% Complete 20% Complete 20% Complete
|
|
| 05 | Door frame fitting work | Ground floor
1st floor 2nd Floor 3rd Floor 4th floor 5th floor 6th floor 7th floor
|
||
| 06 | Sanitary & plumbing line work | Apartment =A1
Apartment=A2 Apartment=A3 Apartment=A4
|
10% Complete
10% Complete 10% Complete 10% Complete
|
|
| 07 | In side Plastering work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7
|
30% Complete
30% Complete 30% Complete 30% Complete 20% Complete 30% Complete
|
|
| 08 | Electrical cable wiring work | |||
| 09 | Wall tiles work | |||
| 10 | Common sanitary & Plumbing line work | |||
| 11 | Outside plastering work | |||
| 12 | Floor tiles/Marble work | |||
| 13 | L.C.C work | |||
| 14 | Grill & Railing work | |||
| 15 | Inside paint & Polishing work | |||
| 16 | Switch -Socket fitting work | |||
| 17 | Outside paint work | |||
| 18 | Door shutter work | |||
| 19 | Aluminum work | |||
| 20 | Tiles Pointing work & Marble finishing work | |||
| 21 | Commode-Basin fitting work and CP fittings work | |||
| 22 | Lift/Generator /Substation /Solar work | |||
| 23 | Boundary wall /Ground floor development work | |||
| 24 | Roof top finishing work | |||
| 25 | Roof top Gardening work G.F Garden work |