Fortune Homes

Bashundhara R/A, Dhaka
Expected Completion Date February 2028
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Foundation Completed
02 Super Structure work 100%
03 Block Work A2 = 80%, B2= 90%, A3 = 90%, B3= 90% ,A4= 90%, B4= 90% ,A5 = 90%, B5= 90% A6= 90%, B6= 90%, A7= 90%, B7= 90%, A8= 90%, B8= 80%, A9=80%, B9= 80%,
04 Electrical conducting work A2 = 80%, B2= 90%, A3 = 90%, B3= 90% ,A4= 90%, B4= 90% ,A5 = 90%, B5= 90% A6= 90%, B6= 90%, A7= 90%, B7= 90%, A8= 90%, B8= 80%, A9=80%, B9= 80%,
05 Door frame fitting work 100%
06 Sanitary & plumbing line work 80%
07 In side Plastering work A2 = 30%, B2= 30%, A3 = 80%, B3= 80%, A4= 80%, B4= 80%, A5 = 70%, B6= 90%, A6= 80%, B6= 80%, A7 = 70%, B7= 90%, A8 = 70%, B8= 90%
08 Electrical cable wiring work N/A
09 Wall tiles work 90%
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 90%
12 Floor tiles/Marble work 70%
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work

 

N/A
25 Roof top Gardening work G.F Garden work N/A

 