Familia

Bashundhara R/A, Dhaka
Expected Completion Date November 2027
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work 100% Completed
02 Super Structure work 100% Completed
03 Block work 98%  Completed
04 Electrical  conduit  work 85% completed
05 Door frame fitting work 80%
06 Sanitary & plumbing line  work 60% complete
07 In side Plastering work 80%
08 Electrical cable wiring work 00 %
09 Wall tiles  work 10%
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 80%
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work 20%
25 Roof top Gardening work N/A