Deja Vu

Aftabnagar, Dhaka
Expected Completion Date April 2028
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed  
02 Super Structure work   100% completed  
03 Block Work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment = A8

Apartment = B8

Apartment = A9

Apartment =B9

 

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

95% Complete

95% Complete

95% Complete

95% Complete

90% Complete

90% Complete

 

 
04 Electrical conduiting work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment = A8

Apartment = B8

Apartment = A9

Apartment =B9

 

85% Complete

85% Complete

85% Complete

85% Complete

85% Complete

85% Complete

85% Complete

85% Complete

85% Complete

85% Complete

80% Complete

80% Complete

80% Complete

80% Complete

80% Complete

80% Complete

 
05 Door frame fitting work Ground floor

1st floor

2nd Floor

3rd Floor

4th floor

5th floor

6th floor

7th floor

8th floor

9th floor

0% Complete

0% Complete

90% Complete

90% Complete

60% Complete

80% Complete

70% Complete

70% Complete

70% Complete

70% Complete

 

 
06 Sanitary & plumbing line work   48% Complete  
07 In side Plastering work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment = A8

Apartment = B8

Apartment = A9

Apartment =B9

 

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

80% Complete

80% Complete

80% Complete

80% Complete

 

 
08 Electrical cable wiring work   14% Complete

 

 
09 Wall tiles work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work   70% Complete  
12 Floor tiles/Marble work      
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode-Basin fitting work and CP fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work   50% Complete  
24 Roof top finishing work   10% Complete  
25 Roof top Gardening work G.F Garden work   10% Complete  