Decoris

Bashundhara R/A, Dhaka
Expected Completion Date April 2027
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Foundation completed
02 Super Structure work 100%
03 Block Work  A1 = 100%, A2= 100%, A9= 100%, A4= 100%, A5= 100%, A6= 100%, A7= 100%,
04 Electrical conducting work Common area 40%, A1 = 100%, A2= 100%, A3= 100%, A4= 100%, A5= 100%, A6= 100%,
05 Door frame fitting work A1 = 100%, A2= 100%, A3= 100% ,A4= 100%, A5= 100% ,A6= 100%
06 Sanitary & plumbing line work N/A
07 In side Plastering work A1 = 100%, A2= 100%, A9= 100%, A4= 100%, A5= 90%, A6= 90%,
08 Electrical cable wiring work 90%
09 Wall tiles work 90%
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 90%
12 Floor tiles/Marble work 90%
13 L.C.C work N/A
14 Grill & Railing work 90%
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work 90%
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work 50%
23 Boundary wall /Ground floor development work 50%
24 Roof top finishing work

 

N/A
25 Roof top Gardening work G.F Garden work N/A