UABL
Construction progress details
The progress table comes directly from the WordPress post content.
| SL. No | Name of the work | Progress details |
| Foundation work | 100% Completed | |
| Super Structure work | 99% completed | |
| Block work | T-1,2,3&4, A-Type=99%, B-Type=99% C-Type=99%, D-Type=99%, | |
| Electrical conduit work` | T-3&4, A-Type=100%, B-Type=100%, C-Type=100%, D-Type=100%,
T-1,2 Type (A)= 98%, B-Type= 98%, C-Type=98%, |
|
| Door frame fitting work | 99% | |
| Sanitary & plumbing line work | 93% | |
| In side Plastering work | 99% | |
| Electrical cable wiring work | 82% | |
| Wall tiles work | 88% | |
| Common Area sanitary & Plumbing line work | 32% | |
| Outside plastering work | 98% | |
| Floor tiles/Marble work | 88% | |
| L.C.C work | 95% | |
| Grill & Railing work | 90% | |
| Inside paint & Polishing work | 30% | |
| Switch -Socket fitting work | N/A | |
| Outside paint work | 25% | |
| Door shutter work | N/A | |
| Aluminum/Glazing work | N/A | |
| Tiles Pointing work & Marble finishing work | N/A | |
| Commode – Basin fitting work and C.P fittings work | N/A | |
| Lift/Generator /Substation /Solar work | N/A | |
| Boundary wall /Ground floor development work | 76% | |
| Roof top finishing work | 65% | |
| Roof top Gardening work | 20% |