Cosmopolis

Mirpur, Dhaka
Expected Completion Date December 2026
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 99% completed
  Block work T-1,2,3&4, A-Type=99%, B-Type=99% C-Type=99%, D-Type=99%,
  Electrical  conduit work` T-3&4, A-Type=100%, B-Type=100%, C-Type=100%, D-Type=100%,

T-1,2 Type (A)= 98%, B-Type= 98%,

C-Type=98%,

  Door frame fitting work 99%
  Sanitary & plumbing line  work 93%
  In side Plastering work 99%
  Electrical cable wiring work 82%
  Wall tiles  work 88%
  Common Area sanitary & Plumbing line work 32%
  Outside plastering work 98%
  Floor tiles/Marble work 88%
  L.C.C work 95%
  Grill & Railing work 90%
  Inside paint & Polishing work 30%
  Switch -Socket fitting work N/A
  Outside paint work 25%
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work 76%
  Roof top finishing work 65%
  Roof top Gardening work 20%

 