City Pointe

Aftabnagar, Dhaka
Expected Completion Date May 2028
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed  
02 Super Structure work   97% completed  
03 Block Work Apartment =A2

Apartment =B2

Apartment =C2

Apartment =D2

Apartment =E2

Apartment =F2

Apartment =G2

Apartment =H2

Apartment =I2

Apartment =J2

Apartment =A3

Apartment =B3

Apartment =C3

Apartment =D3

Apartment =E3

Apartment =F3

Apartment =G3

Apartment =H3

Apartment =I3

Apartment =J3

Apartment =A4

Apartment =B4

Apartment =C4

Apartment =D4

Apartment =E4

Apartment =F4

Apartment =G4

Apartment =H4

Apartment =I4

Apartment =J4

Apartment =A5

Apartment =B5

Apartment =C5

Apartment =D5

Apartment =E5

Apartment =F5

Apartment =G5

Apartment =H5

Apartment =I5

Apartment =J5

Apartment =A6

Apartment =B6

Apartment =C6

Apartment =D6

Apartment =E6

Apartment =F6

Apartment =G6

Apartment =H6

Apartment =I6

Apartment =J6

Apartment =A7

Apartment =B7

Apartment =C7

Apartment =D7

Apartment =E7

Apartment =F7

Apartment =G7

Apartment =H7

Apartment =I7

Apartment = J7

 

Apartment =A8

Apartment =B8

Apartment =C8

Apartment =D8

Apartment =E8

Apartment =F8

Apartment =G8

Apartment =H8

Apartment =I8

Apartment = J8

Apartment =A9

Apartment =B9

Apartment =C9

Apartment =D9

Apartment =E9

Apartment =F9

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

90% Complete

90% Complete

90% Complete

90% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

90% Complete

90% Complete

90% Complete

90% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

88% Complete

88% Complete

85% Complete

88% Complete

90% Complete

90% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

80% Complete

80% Complete

80% Complete

80% Complete

80% Complete

80% Complete

95% Complete

95% Complete

95% Complete

95% Complete

65% Complete

65% Complete

65% Complete

65% Complete

89% Complete

85% Complete

 

 

 

 
04 Electrical conduiting work Apartment =A2

Apartment =B2

Apartment =C2

Apartment =D2

Apartment =E2

Apartment =F2

Apartment =G2

Apartment =H2

Apartment =I2

Apartment =J2

Apartment =A3

Apartment =B3

Apartment =C3

Apartment =D3

Apartment =E3

Apartment =F3

Apartment =G3

Apartment =H3

Apartment =I3

Apartment =J3

Apartment =A4

Apartment =B4

Apartment =C4

Apartment =D4

Apartment =E4

Apartment =F4

Apartment =G4

Apartment =H4

Apartment =I4

Apartment =J4

 

Apartment =A5

Apartment =B5

Apartment =C5

Apartment =D5

Apartment =E5

Apartment =F5

Apartment =G5

Apartment =H5

Apartment =I5

Apartment =J5

 

Apartment =A6

Apartment =B6

Apartment =C6

Apartment =D6

Apartment =E6

Apartment =F6

Apartment =G6

Apartment =H6

Apartment =I6

Apartment =J6

 

Apartment =A7

Apartment =B7

Apartment =C7

Apartment =D7

Apartment =E7

Apartment =F7

Apartment =G7

Apartment =H7

Apartment =I7

Apartment =J7

 

Apartment =A8

Apartment =B8

Apartment =C8

Apartment =D8

Apartment =E8

Apartment =F8

Apartment =G8

Apartment =H8

Apartment =I8

Apartment =J8

 

Apartment =A9

Apartment =B9

Apartment =C9

Apartment =D9

Apartment =E9

Apartment =F9

 

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

85% Complete

85% Complete

85% Complete

85% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

75% Complete

75% Complete

75% Complete

75% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

75% Complete

75% Complete

75% Complete

75% Complete

80% Complete

80% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

75% Complete

75% Complete

75% Complete

75% Complete

75% Complete

75% Complete

95% Complete

95% Complete

95% Complete

95% Complete

 

65% Complete

65% Complete

65% Complete

65% Complete

85% Complete

85% Complete

 

 
05 Door frame fitting work Ground floor

1st floor

2nd Floor

3rd Floor

4th floor

5th floor

6th floor

7th floor

8th floor

9th floor

0% Complete

0% Complete

100% Complete

100% Complete

100% Complete

100% Complete

80% Complete

70% Complete

65% Complete

40% Complete

 

 
06 Sanitary & plumbing line work   55% Complete  
07 In side Plastering work Apartment =A2

Apartment =B2

Apartment =C2

Apartment =D2

Apartment =E2

Apartment =F2

Apartment =G2

Apartment =H2

Apartment =I2

Apartment =J2

 

Apartment =A3

Apartment =B3

Apartment =C3

Apartment =D3

Apartment =E3

Apartment =F3

Apartment =G3

Apartment =H3

Apartment =I3

Apartment =J3

Apartment =A4

Apartment =B4

Apartment =C4

Apartment =D4

Apartment =E4

Apartment =F4

Apartment =G4

Apartment =H4

Apartment =I4

Apartment =J4

Apartment =A5

Apartment =B5

Apartment =C5

Apartment =D5

Apartment =E5

Apartment =F5

Apartment =G5

Apartment =H5

Apartment =I5

Apartment =J5

 

Apartment =A6

Apartment =B6

Apartment =C6

Apartment =D6

Apartment =E6

Apartment =F6

Apartment =G6

Apartment =H6

Apartment =I6

Apartment =J6

 

Apartment =A7

Apartment =B7

Apartment =C7

Apartment =D7

Apartment =E7

Apartment =F7

Apartment =G7

Apartment =H7

Apartment =I7

Apartment =J7

 

Apartment =A8

Apartment =B8

Apartment =C8

Apartment =D8

Apartment =E8

Apartment =F8

Apartment =G8

Apartment =H8

Apartment =I8

Apartment =J8

 

Apartment =A9

Apartment =B9

Apartment =C9

Apartment =D9

Apartment =E9

Apartment =F9

 

 

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

 

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

90% Complete

90% Complete

90% Complete

90% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

10% Complete

10% Complete

10% Complete

10% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

 

50% Complete

20% Complete

50% Complete

20% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

 

40% Complete

0% Complete

40% Complete

0% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

 

30% Complete

0% Complete

30% Complete

0% Complete

60% Complete

60% Complete

90% Complete

90% Complete

80% Complete

80% Complete

 

10% Complete

0% Complete

10% Complete

0% Complete

70% Complete

70% Complete

 
08 Electrical cable wiring work   15% Complete  
09 Wall tiles work   5% Complete  
10 Common sanitary & Plumbing line work   20% Complete  
11 Outside plastering work   35% Complete  
12 Floor tiles/Marble work   0% Complete  
13 L.C.C work   0% Complete  
14 Grill & Railing work   15% Complete  
15 Inside paint & Polishing work   0% Complete  
16 Switch -Socket fitting work   0% Complete  
17 Outside paint work   0% Complete  
18 Door shutter work   0% Complete  
19 Aluminum work   0% Complete  
20 Tiles Pointing work & Marble finishing work   0% Complete  
21 Commode-Basin fitting work and CP fittings work   0% Complete  
22 Lift/Generator /Substation /Solar work   0% Complete  
23 Boundary wall /Ground floor development work   35% Complete  
24 Roof top finishing work   70% Complete  
25 Roof top Gardening work G.F Garden work   20% Complete  

 