Beverly Residence

Gulshan, Dhaka
Expected Completion Date September 2027
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work 100 % Completed
02 Super Structure work 100% Completed
03 Block Work 98% Completed
04 Electrical conducting work 95% Completed
05 Door frame fitting work 100% Completed
06 Sanitary & plumbing line work 80% Completed
07 In side Plastering work 90% Completed
08 Electrical cable wiring work 60% Completed
09 Wall tiles& floor tiles work 80% Completed

 

10 Common sanitary & Plumbing line work 60% Completed
11 Outside plastering work 85% Completed
12 Floor tiles/Marble work 80% Completed
13 L.C.C work Not Yet Started
14 Grill & Railing work 40% Completed
15 Inside paint & Polishing work Not Yet Started
16 Switch -Socket fitting work Not Yet Started
17 Outside paint work Not Yet Started
18 Door shutter work Not Yet Started
19 Aluminum/Glazing work Not Yet Started
20 Tiles Pointing work & Marble finishing work Not Yet Started
21 Commode – Basin fitting work and C.P fittings work Not Yet Started
22 Lift/Generator /Substation /Solar work Not Yet Started
23 Boundary wall /Ground floor development work 28% Completed
24 Roof top finishing work 50% Completed
25 Roof top Gardening work Not Yet Started
26 Gardening work 60% Completed
27 Fair face finishing Not Yet Started
28 Artificial fair face Not Yet Started
29 Kitchen ver. Railing Not Yet Started
30 Outside AC lover Not Yet Started
31 Fir work Not Yet Started
32 Swimming pool works Not Yet Started
32 Pavement tiles Not Yet Started
33 Pvc false ceiling works Not Yet Started