Avalon

Uttara, Dhaka
Expected Completion Date October 2027
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work 100% completed. Pile work completed. Cap casting completed.
02 Super Structure work 100 % Completed. (Ground Floor Roof Slab 100% Completed. 1F Roof Slab 100% completed, 2F Roof Slab 100% completed, 3F Roof Slab 100% completed. 4F roof slab 100% completed, 5F roof slab 100% completed, 6th Floor Roof Slab 100% completed, 7th floor roof slab 100% completed. 8th floor roof slab 100% completed)
03 Partition Wall Work 100% Completed.
04 Electrical conduiting work 95% Completed.
05 Door frame fitting work 100% Completed
06 Sanitary & plumbing line work 90% Completed.
07 In side Plastering work 90% Completed.
08 Electrical cable wiring work 90% Completed.
09 Wall tiles& floor tiles work 75% Completed.
10 Common sanitary & Plumbing line work 60% Completed.
11 Outside plastering work 100% Completed.
12 Floor tiles/Marble work 70% Completed.
13 L.C.C work Not yet started.
14 Grill & Railing work 70% Completed.
15 Inside paint & Polishing work Not yet started.
16 Switch -Socket fitting work Not yet started.
17 Outside paint work Not yet started.
18 Door shutter work Not yet started.
19 Aluminum/Glazing work Not yet started.
20 Tiles Pointing work & Marble finishing work Not yet started.
21 Commode – Basin fitting work and C.P fittings work Not yet started.
22 Lift/Generator /Substation /Solar work Received
23 Boundary wall /Ground floor development work 80% Completed.
24 Roof top finishing work 70% Completed.
25 Roof top Gardening work Not yet started.
26 Gardening work Not yet started.
27 Fair face finishing Not yet started.
28 Artificial fair face Not yet started.
29 Kitchen ver. Railing Not yet started.
30 Outside AC lover Not yet started.
31 Fir work 50% Completed.
32 Swimming pool works Not yet started.
32 Pavement tiles Not yet started.
33 Pvc false ceiling works Not yet started.