Amabilia

Mohakhali, Dhaka
Expected Completion Date October 2026
Status Updated October, 2026
Back to all projects
UABL

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work 100 % Completed
02 Super Structure work 100 % Completed
03 Block work 100 % Completed
03 Panel Work 100 % Completed
05 Electrical conduiting work 98 % Completed
06 Door frame fitting work 100 % Completed
07 Sanitary & plumbing line work 99 % Completed
08 In side Plastering work 99 % Completed
09 Electrical cable wiring work 98 % Completed
10 Wall tiles& floor tiles work 99% Completed
11 Common sanitary & Plumbing line work 96 % Completed
12 Outside plastering work 100 % Completed
13 Floor tiles/Marble work 100 % Completed
14 L.C.C work 100 % Completed
15 Grill & Railing work 99 % Completed
16 Inside paint & Polishing work 90 % Completed
17 Switch -Socket fitting work 90 % Completed
18 Outside paint work 80 % Completed
19 Door shutter work 98 % Completed
20 Aluminum/Glazing work 95 % Completed
21 Tiles Pointing work & Marble finishing work 95 % Completed
22 Commode – Basin fitting work and C.P fittings work 90 % Completed
23 Lift/Generator /Substation /Solar work 90 % Completed
24 Boundary wall /Ground floor development work 90 % Completed
25 Roof top finishing work 90 % Completed
26 Roof top Gardening work 80% Completed
27 Gardening work 40% Completed
28 Fair face finishing 90 % Completed
29 Artificial fair face 92% Completed
30 Kitchen ver. Railing 100 % Completed
31 Outside AC lover 80 % Completed
32 Fire Fighting work 80 % Completed
33 Swimming pool works N/A
34 Pavement tiles 95 % Completed
35 False ceiling works 81% Completed.