Construction progress details
The progress table comes directly from the WordPress post content.
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | 100 % Completed |
| 02 | Super Structure work | 100 % Completed |
| 03 | Block work | 100 % Completed |
| 03 | Panel Work | 100 % Completed |
| 05 | Electrical conduiting work | 98 % Completed |
| 06 | Door frame fitting work | 100 % Completed |
| 07 | Sanitary & plumbing line work | 99 % Completed |
| 08 | In side Plastering work | 99 % Completed |
| 09 | Electrical cable wiring work | 98 % Completed |
| 10 | Wall tiles& floor tiles work | 99% Completed |
| 11 | Common sanitary & Plumbing line work | 96 % Completed |
| 12 | Outside plastering work | 100 % Completed |
| 13 | Floor tiles/Marble work | 100 % Completed |
| 14 | L.C.C work | 100 % Completed |
| 15 | Grill & Railing work | 99 % Completed |
| 16 | Inside paint & Polishing work | 90 % Completed |
| 17 | Switch -Socket fitting work | 90 % Completed |
| 18 | Outside paint work | 80 % Completed |
| 19 | Door shutter work | 98 % Completed |
| 20 | Aluminum/Glazing work | 95 % Completed |
| 21 | Tiles Pointing work & Marble finishing work | 95 % Completed |
| 22 | Commode – Basin fitting work and C.P fittings work | 90 % Completed |
| 23 | Lift/Generator /Substation /Solar work | 90 % Completed |
| 24 | Boundary wall /Ground floor development work | 90 % Completed |
| 25 | Roof top finishing work | 90 % Completed |
| 26 | Roof top Gardening work | 80% Completed |
| 27 | Gardening work | 40% Completed |
| 28 | Fair face finishing | 90 % Completed |
| 29 | Artificial fair face | 92% Completed |
| 30 | Kitchen ver. Railing | 100 % Completed |
| 31 | Outside AC lover | 80 % Completed |
| 32 | Fire Fighting work | 80 % Completed |
| 33 | Swimming pool works | N/A |
| 34 | Pavement tiles | 95 % Completed |
| 35 | False ceiling works | 81% Completed. |